Investment Planning

Financial Roadmap & Projected Returns

📅 Timeline & Milestones

0-3 Months

Texas Team Setup

Site selection, land & factory contracts, utilities setup, initial permits.

Inv: $5.0M
3-6 Months

Design Procurement

Design plans, city permits, procurement intent orders.

6-12 Months

1GWh Production Line

European procurement of materials, processing 3kton.

Inv: $30.0M
12-20 Months

DOE Funding & Expansion

Apply for DOE funding, expand phosphoric iron production line.

Inv: $60.0M
20-32 Months

Full Production

Full element production, 50kton production line.

📈 Investment & Return

300M150M0M
0m6m12m20m32m
Cumulative Investment
Projected Profit